Home » LPG Tank » Liquefied gas storage tank pipeline acceptance inspection

Liquefied gas storage tank pipeline acceptance inspection

2 Appearance inspection   2.1 Appearance inspection shall include inspection of various piping components, piping support parts and inspection during pipeline construction.   2.2 The insp...
Rated 4.7/5 based on 324 customer reviews
Share:
Content

2 Appearance inspection

 

2.1 Appearance inspection shall include inspection of various piping components, piping support parts and inspection during pipeline construction.

 

2.2 The inspection quantities and standards of pipeline components, pipeline support pieces, pipeline processing parts, groove processing and assembly, and pipeline installation shall comply with the relevant provisions of the specification GB50235.

 

2.3 Except for the welds with special requirements in the welding operation instructions, the slag and spatter shall be removed immediately after welding, and the surface of the welds shall be cleaned for visual inspection.

Inquiry


    More LPG Tank