Liquid feeding operation procedure

As soon as you receive information of liquid feeding, get ready in accordance with the unloading truck and compressor operating process.

Rated 4.7/5 based on 570 customer reviews
Share:
Content

1、As soon as you receive information of liquid feeding, get ready in accordance with the unloading truck and compressor operating process.
2、Open the liquid-phase inlet valve of the tank to be fed with the liquid-phase pipe of the tanker, open the gas-phase valve of the corresponding tank and connect it with the inlet of the compressor, and connect the gas-phase of the tanker with the outlet of the compressor.
3, into the liquid process should pay attention to the tank pressure does not exceed 1.8MPA, the liquid level does not exceed 85%, overfilling is strictly prohibited, such as found overfilling immediately pouring tanks.