Safety Precautions for LPG Station Engineering
2.1. Prevent open flames.
2.2. Leakage prevention.
Since this project is an expansion project, it needs to be connected with the original pipeline. The original pipeline may have residual liquefied petroleum gas. If it is directly welded without treatment, it may cause an explosion, which is very dangerous; so before construction, first connect it with the storage tank Close all the connected valves, rinse the pipeline with water several times, and then open the valve connected to the pipeline to let the pipeline communicate with the atmosphere. After two days of stopping, the liquefied gas in the pipeline is drained, and then start construction. When welding with the original connection, send a safety officer to observe by holding a fire extinguisher.