The first link in our chain of producing LPG ring tanks is head processing
The first link in our chain of producing LPG ring tanks is head processing
1、Material confirmation 2、Carry the confirmed material to the shelf ring by crane 3、Start the unscrewing machine to implement automatic uncoiling and unscrewing. 4、Check the surface condition. 5、Automatic press drop by hydraulic press 6、Stack the garden piece neatly and make material marking transplant. 7、Clean the edge material to the designated area for storage. Our requirement is that the internal height of the head is not less than 272+2 and the wall thickness of the head The thinning amount is not more than 10% of the material thickness, and the actual measured wall thickness is not less than 2.5mm, no wrinkle, the The error of garden degree is less than 2㎜, and the surface is free of scratches. Advance in order, if different batches are encountered, they should be marked mark and isolate.